Start to Finish Relationship Explanation

SF as per PMBOK5 SF as per Lalit

As per PMBOK5 the definition of Start to Finish Relationship is: A logical relationship in which a successor activity cannot finish until a predecessor activity has started.

The same has been shown in the link  “SF as per PMBOK5” above.

However a better interpretation of this relationship will be as follows: A logical relationship in which the predecessor (although it may be happening later in time) DECIDES or DICTATES the finishing of the successor activity.

The same as been shown in link “SF as per Lalit” above.

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s