Ans of Quiz Q1:

In layman’s language, predecessor means some thing which happens earlier. But in project management terminology, predecessor means the primary activity and successor means the dependent activity. Therefore the event A “Boss Going to Office” is the predecessor and event B “Driver making the car ready” is successor event.

As the process of making the car ready must be over by the time the boss starts for office with a buffer of 15 minutes, the best relationship to link them will be SF (Start to Finish relationship) with a lead of 15 minutes.